Utility Department
 

Wastewater Division

Wastewater Plant Update

Posted: January 6, 2009

Update December 2008: (Click on thumbnails to view pictures larger)

Influent Pump Station (IPS) After some final details connecting discharge piping to the IPS pumps, a temporary loop of piping was set up to send water (reclaimed water, not sewage) back from the new secondary clarifiers to the IPS for the IPS pumps to send through the grit treatment unit and the oxidation ditches then on to the secondary clarifiers again. This water loop testing is required in the construction contract to demonstrate the new facilities meet operational requirements.

Click here to see a video of the
temporary water loop discharge


IPS Pump Discharge Header


Temporary Discharge
Piping to IPS Wetwell

Oxidation Ditches (ODs) In November, the ODs starting filling with reclaimed water. Once full, the propeller mixers and recirculation pumps were placed in service as part of the water loop operational testing procedure. Some final detail work was completed on the OD aeration blowers, such as installation of blower and air piping insulation.


OD Propeller Mixers
(as installed in July)

Aerated Water
Circulating in OD

OD Aeration
Diffuser Areas

OD Blowers with Insulation

Secondary Clarifiers A temporary pump station was set up to suck the water from the secondary clarifiers and return it to the IPS for recirculation.


Temporary Suction Piping
(2 white vertical pipes)
and Portable Pumps
(green units)

Grease Receiving Station Concrete Slab Pour

Completed Grease
Receiving Station

Solids Handling The grease and scum from the secondary clarifiers will be pumped to the 2 Dissolved Air Floatation Thickeners (DAFTs). Quite a bit of work was completed at these units in December including completion of the area concrete slab and installation of the associated equipment. Roofs were installed on the circular tanks to capture and control any odors which may be generated in these units. This “foul air” will be removed by blowers and diffused through a scrubbing media. The material of the media is wood chips and compost which promotes the growth of an odor removing bacterium.


DAFT Area Slab

DAFT Air Saturation Tank

DAFT Pressurization Pumps

DAFT Tank Roof

Foul Air Blower

Foul Air Biofilter
(without media)

Secondary Effluent Equalization Pump Station (SEEPS) When the plant flow is normal (without all the temporary water recirculation loops for testing), the water leaving the secondary clarifiers will flow to an equalization tank for temporary storage of each day’s peak flow. After the peak flow has diminished to lower flows, this stored peak water will be pumps out of the tank by the SEEPS. Much work was completed in December on this SEEPS structure including construction of the pump station’s top slab and the installation of a retaining wall.


SEEPS Top Slab Concrete Pour

Concrete Finishing Work SEEPS Top Slab

SEEPS Retaining Wall

SEEPS Pumps Electrical Equipment Installed

Power and Controls The electrical subcontractor was very busy pulling power and control wires throughout the project site. Some finishing work such as installation of lighting around units and roads was also completed.


Pulling Wire from Admin Building to Filter/UV Building

Miscellaneous Some smaller items were completed, for example the installation of the pumps for the plant’s new second storm water pump station and installation of some channel grating. Also, work continued on the site final grading in preparation for road paving scheduled for early 2009. Training in December was a little reduced due to the holidays, but Staff did learn about some new equipment such as the submersible solids-pumping secondary scum/grease pumps.


Storm Water Pumps

Concrete Apron for
New Roadway

Grading for Pavement
Near Grit Unit
 
Submersible Pump Training

OD Inlet Channel Grating and Protective Bollards

Check back again in February to see what happened in January.

 

Previous Months

 
Copyright © 2009 - City of Lompoc
All rights reserved
Lompoc, California 93438